In This Article
What Is a Cofferdam?
A cofferdam is a temporary watertight enclosure built in, around, or adjacent to water so that the area enclosed can be kept dry during construction. Think of it as a temporary dam β a structure that holds water out (and sometimes holds soil in) while workers construct foundations, piers, tunnels, and utilities in the dry.
Cofferdams are inherently temporary: they are constructed, used during a specific construction phase, and then removed (or, in some cases, incorporated into the permanent structure as a sacrificial form). Their design must account for the temporary nature β typically designed for the construction period load cases rather than the full service life environmental loads of permanent structures.
When Are Cofferdams Used in NYC?
- Bridge pier construction and repair (East River, Harlem River, Hudson River crossings)
- Waterfront pile cap and footing concrete placement (piers, bulkheads, seawalls)
- Utility and subway tunnel crossings below waterways
- Foundation construction adjacent to tidal waterways where groundwater is too high for conventional open-cut excavation
- Drydock and marine facility maintenance and construction
- Intake and outfall structure construction for water and wastewater facilities
Cofferdam Types
| Type | Description | Best For |
|---|---|---|
| Steel sheet pile cofferdam | Interlocked Z or U-section sheet piles driven into riverbed forming a closed perimeter; interior dewatered; walers and struts provide lateral support | Most NYC applications; rivers and harborways; depths up to 40β50 ft |
| Cellular cofferdam | Circular cells of flat sheet piles filled with granular fill; self-supporting gravity structure | Wide cofferdams; areas with hard soils limiting sheet pile penetration |
| Earth-filled cofferdam | Earthen dike with impermeable core; used when large areas enclosed at relatively shallow depth | Marshes, shallow water; typically not practical in urban NYC |
| Double-wall cofferdam | Two parallel rows of sheet piles with fill between; used where single-wall system is inadequate | Deep water locations; tidal range > 15 ft |
Structural Design of Sheet Pile Cofferdams
The structural engineer designs a sheet pile cofferdam for the following load cases and failure modes:
- Active earth pressure: Soil pressure on the landward side of the sheet pile pushing inward β calculated using Rankine or Coulomb theory
- Hydrostatic pressure: Water pressure differential across the sheet pile wall β highest when interior is fully dewatered and exterior is at high tide or flood stage
- Passive resistance: Soil resistance at the embedded toe of the sheet pile β provides stability against sliding and overturning
- Seepage forces: Upward seepage beneath the embedded toe (heave) β a critical failure mode in soft clays
- Wave and current loading: Tidal currents and wave action in NYC waterways add dynamic lateral loads
The design output includes: required sheet pile section modulus (selecting minimum pile section); embedment depth; waler beam sizing (horizontal channels or wide-flange beams); strut design (axial compression members spanning across the cofferdam interior); and confirmation of global stability against overturning and base heave.
Dewatering: Process and Discharge Requirements
Once the sheet pile perimeter is complete and joints are sealed (using bentonite or water expansive grout at problem areas), dewatering pumps remove water from the interior. Dewatering considerations in NYC:
- Pump sizing: Must overcome both initial drawdown volume and continuous seepage inflow through sheet pile joints and the soil below the pile toe
- Discharge water quality: Dewatering discharge into NYC waterways or storm drains must meet NYC DEP water quality standards β turbidity, pH, hydrocarbon content. Sedimentation tanks or dewatering bags may be required before discharge
- Groundwater monitoring: Piezometers monitor the groundwater table outside the cofferdam to detect excessive drawdown that could cause settlement of adjacent structures with shallow foundations
NYC & Federal Permit Requirements
Cofferdam work in NYC waterways requires a multi-agency permit package:
| Agency | Permit | Trigger |
|---|---|---|
| US Army Corps of Engineers (USACE) | Section 10 (Rivers and Harbors Act) | Work in navigable waterways |
| USACE | Section 404 (Clean Water Act) | Fill in waters of the US |
| NYC DEP | Waterway permit | In-water work in NYC waterways |
| NYC DEP | SPDES / Dewatering permit | Discharge of dewatering effluent |
| NYC Parks Department | Revocable Consent | Work in mapped parkland/waterfront park |
| NYC DOT | Street opening permit / ROW permit | Work affecting public streets or bridges |
| NYSDEC | Tidal wetlands / freshwater wetlands permit | Work in state-regulated wetland areas |
Adjacent Structure Settlement Risks
In densely built NYC, cofferdam dewatering poses a significant risk to adjacent buildings with shallow foundations. When the groundwater table is lowered:
- Foundations in sand or silt that previously provided uplift support may lose capacity, causing settlement
- Timber piles from historic NYC construction may be exposed to air and desiccate if the water table drops below their tops β causing rapid timber decay and column settlement
Mitigation measures include: recharge wells outside the cofferdam perimeter to maintain the water table in sensitive zones; pre-construction condition surveys of adjacent buildings; and settlement monitoring with precision survey and vibrating wire settlement plates during the entire dewatering period.
Cofferdam Removal
When permanent construction inside the cofferdam is complete, the cofferdam is removed. Sheet piles are extracted using vibro-hammers (the same equipment used for installation). The extraction process must be engineered: the permanent structure must be able to support itself independently before cofferdam support is removed. Permanent waterfront structures typically include internal bracing or rely on the completed concrete structure's own weight and embedment for stability. Where sheet pile extraction might cause ground disturbance adjacent to existing utilities or structures, the piles may be cut off below grade and left in place.
Frequently Asked Questions
A cofferdam is a temporary watertight enclosure that allows construction to proceed in the dry in or adjacent to water. In NYC, cofferdams are used for bridge pier work, waterfront foundation construction, utility crossings below waterways, and below-water-table excavations. Steel sheet pile cofferdams are the most common type for NYC waterway applications.
Cofferdam work in NYC navigable waterways requires: USACE Section 10 permit; USACE Section 404 permit; NYC DEP waterway permit; NYC DEP SPDES dewatering discharge permit; potentially NYSDEC tidal/freshwater wetlands permit; NYC DOT street permit; and standard NYC DOB construction permits. The permitting process typically requires 3β6 months, and environmental review (CEQR/SEQRA) may apply to larger projects.
Steel sheet pile cofferdams (interlocked Z-section piles driven into the riverbed, with internal walers and struts) are the standard system for most NYC waterway applications. Cellular cofferdams are used for wider enclosures or hard-soil conditions. The PE designs for earth pressure, hydrostatic pressure, seepage heave, and wave/current loading.
Submersible pumps dewater the interior of the cofferdam. Discharge water must meet NYC DEP quality standards before release. Settlement monitoring is critical β dewatering can lower the water table outside the cofferdam and damage adjacent foundations (particularly timber piles from historic construction). Recharge wells may be used to maintain the water table in sensitive zones.
Cofferdams are designed by licensed structural engineers (PE) with geotechnical expertise, or by a team of structural and geotechnical engineers. The design includes earth and hydrostatic pressure analysis, sheet pile section selection, waler and strut sizing, and stability checks for overturning and base heave. PE-stamped cofferdam drawings are required for the construction permit.
Cofferdam & Water Diversion Engineering β New York City
Asvakas Engineering designs sheet pile cofferdams, dewatering systems, and waterfront temporary works for NYC construction projects β with full coordination of multi-agency permitting requirements.
Request Cofferdam Engineering