In This Article
What Is Construction Administration?
Construction administration (CA) is the phase of structural engineering service that occurs during the actual physical construction of the project. After the engineer of record (EOR) completes construction documents and the building permit is issued, the contractor takes possession of the site and begins building. The CA phase begins at that point and continues through substantial completion.
During CA, the structural engineer's role transitions from creator to verifier: the engineer is not managing the construction or directing the contractor's means and methods, but is rather the technical authority who confirms that what is being built is structurally consistent with what was designed. This distinction β the EOR as design authority, the contractor as construction authority β is fundamental to understanding CA responsibilities.
Why CA Is Critical for Quality
Industry data consistently shows that a large proportion of structural defects arise not from design errors but from construction-phase deviations from the design intent. These include: substituted materials identified as equivalent but not actually equivalent; field modifications made to accommodate MEP routing without structural review; installation errors in connection bolting or welding; insufficient concrete consolidation around complex reinforcement; and anchor installation that doesn't match the approved drawings.
Without the structural engineer's CA involvement, these deviations may not be caught until long after construction is complete β if ever. Once a defect is concealed by subsequent construction, the cost of discovery and remediation multiplies enormously. Regular CA oversight is the most cost-effective quality control investment an owner can make.
Shop Drawing & Submittal Review
Before structural work is fabricated or installed, the contractor must submit shop drawings β detailed fabrication or installation drawings prepared by the fabricator or specialty contractor β for engineer review. For structural scope, key submittals include:
- Structural steel shop drawings: Fabricator's drawings showing all member sizes, connection details, weld sizes, bolt layouts, and erection sequences. The EOR reviews for compliance with structural design intent and AISC/AWS requirements.
- Rebar shop drawings: Bar placement drawings and bar lists prepared by the rebar detailer showing bar sizes, spacing, lap splice lengths, development lengths, and cover dimensions.
- Concrete mix designs: Batch plant records confirming the specified concrete compressive strength (f'c), water-cement ratio, and admixtures.
- Anchor bolt submittals: ICC-ES evaluation reports and installation instructions for post-installed concrete anchors.
The review process is sequential: submittal transmitted β logged into submittal tracking system β reviewed by EOR β returned with stamp (Approved, Approved as Noted, Revise & Resubmit, or Rejected). The EOR typically has 10 working days per AIA contract standards to complete review.
RFI Process
An RFI (Request for Information) is a formal written inquiry from the contractor to the design team requesting clarification of the construction documents. Structural RFIs arise when: drawings are not sufficiently detailed for a specific installation; two drawings conflict with each other; field conditions differ from the design assumption; or the contractor wants to propose a substitution or deviation.
The EOR's response to an RFI must be technically correct, clearly worded, and timely. A delayed RFI response that sits in a reviewer's queue while the contractor is actively working on the related activity creates legitimate grounds for a time extension claim. Best practice is to track all open RFIs in a log with target response dates and follow up proactively.
Site Observation Visits
Periodic site observation visits by the EOR provide direct visual verification that construction is proceeding in general conformance with the contract documents. Site visits are not continuous β the contractor is not supervised by the engineer on a daily basis. Rather, visits are scheduled at key structural milestones: foundation element placement, structural steel erection, post-tensioning operations, pre-pour concrete inspections, and at substantial completion.
Every site visit should be documented with a field report that notes: date, attendees, areas inspected, observations (conforming and non-conforming conditions), and required follow-up actions. Field reports serve as contemporaneous evidence of the engineer's CA performance and are key exhibits if construction defects are later disputed.
Change Orders & Supplemental Instructions
Changes to structural scope during construction are addressed through two primary vehicles:
- Supplemental Instructions: Clarifications or minor changes that don't affect contract price or schedule. Examples: clarifying an ambiguous detail; specifying a connection size not otherwise indicated. Issued unilaterally by the design team.
- Change Orders: Changes that affect scope, price, or schedule. All structural changes involving member size, connection type, opening locations, or material specifications require PE-stamped revised drawings and a formal change order executed by all contract parties.
Special Inspections Coordination
In NYC, the NYC Building Code Chapter 17 mandates special inspections for all structural concrete, structural steel, high-strength bolting, and other specified materials and activities. Special inspections are performed by certified Special Inspectors employed by a special inspection agency that is independent of the contractor. The EOR provides the Statement of Special Inspections (SOSI) with the structural drawings, defining what inspections are required, when, and at what frequency.
Coordinating special inspections is a CA responsibility often underestimated in complexity. The EOR must review inspection reports, respond to non-conformance reports (NCRs) issued by the Special Inspector, and confirm that all required inspections have been completed before sign-off on the Certificate of Occupancy application.
Engineer Authority vs. Contractor Responsibility
The structural engineer of record holds design authority β the legal responsibility for the structural design's compliance with applicable codes and its ability to safely carry the specified loads. The contractor holds construction authority β the legal responsibility for the means and methods of construction, the safety of the construction site, and building the project in conformance with the approved drawings and specifications.
This division matters practically: the EOR cannot direct the contractor's workers, cannot instruct a specific crane move, and cannot accept legal responsibility for construction safety. But the EOR can and must stop the work (through the owner) if construction is observed to be proceeding in a manner that will result in structural non-conformance with the approved design.
Frequently Asked Questions
CA is the phase of structural engineering service during construction. The engineer reviews submittals, responds to RFIs, performs site visits, coordinates special inspections, and evaluates change orders β ensuring what gets built matches what was designed.
A site visit by the EOR is a periodic check for general conformance. A special inspection is a mandatory, code-required inspection by a certified Special Inspector at specific construction activities (concrete pours, steel erection, high-strength bolting). Both are required on most NYC structural projects.
AIA contracts typically allow 10 working days. For critical-path RFIs where construction is actively waiting, 24β48 hours is appropriate. Timely RFI response is one of the engineer's most important obligations during CA β delays create legitimate time extension claims.
Any change affecting structural capacity, code compliance, member sizes, connection types, or material specifications requires PE-stamped revised drawings and a formal change order. Minor clarifications that don't affect structural performance can be issued as Supplemental Instructions.
Full-Service Structural CA in NYC
Asvakas Engineering provides construction administration β submittal review, RFI responses, site visits, and special inspection coordination β for structural projects across New York City.
Request CA Services