What Is Formwork and What Does It Include?

Formwork is the complete temporary construction system that holds fresh concrete in place until it achieves enough strength to be self-supporting. It is a multi-component system:

  • Sheathing (form face or decking): The surface in contact with the fresh concrete. Typically plywood (structural sheathing, HDO or MDO), steel deck forms for slabs, or prefabricated steel panel forms for walls and columns. The sheathing carries the direct fluid pressure of the fresh concrete and transfers it as a line load to the supporting framing.
  • Studs and walers (for wall and column forms): Vertical studs span between walers, carrying the concrete lateral pressure as a uniform distributed load. Wales (horizontal members) span between ties or vertical supports and deliver the lateral pressure as concentrated loads to the tie system or vertical shores.
  • Form ties: Devices (snap ties, she-bolts, coil ties) that resist the lateral pressure pushing the two faces of a wall form apart. They also leave cone holes or recesses in the finished concrete that must be patched.
  • Shoring and reshoring: The vertical load-carrying system — Acrow props, adjustable steel shore posts, tube-and-clamp scaffolding, engineered aluminum frames (system shoring) — that transfers the weight of the slab form, fresh concrete, construction live loads, and equipment down to the ground or previously hardened floors.
  • Bracing: Diagonal bracing of the shoring system for stability against lateral loads — wind, construction equipment impact, eccentricity from uneven concrete placement, and vibration from form vibrators.

Vertical Load Design: Dead + Live + Construction Loads

The vertical load on formwork shoring is the sum of:

Load ComponentValueNotes
Fresh concrete dead load150 pcf × slab thicknessStandard concrete unit weight; use 145 pcf for lightweight
Formwork self-weight5–15 psfDepends on system — aluminum forms lighter than timber
Construction live load (workers + equipment)Minimum 50 psf or 75 psf if motorized equipment used (ACI 347)Never less than 2,000 lb concentrated load for any single hydraulic line or drop head
Impact from concrete pump discharge25 psf minimum (ACI 347)Must be added on top of normal construction LL where pump discharge occurs
Lateral loads (bracing)Minimum 2% of total vertical load (OSHA) distributed laterally, or wind per ASCE 7Bracing must be designed for whichever is greater

For a typical 10-inch CIP concrete slab in NYC: 125 psf (concrete) + 10 psf (formwork) + 75 psf (construction LL) + 25 psf (pump) = 235 psf design load on shoring. This figure surprises many contractors who budget only the slab dead load.

Lateral Pressure of Fresh Concrete: ACI 347 Formulas

For slab forming, only vertical loads matter. For wall and column forming, the lateral (hydrostatic) pressure of fresh concrete governs the wall form and tie design. Fresh concrete behaves as a fluid initially — it exerts full hydrostatic pressure against form faces, equal to 150h psf where h is the height of fluid concrete above the point of consideration.

As the concrete stiffens and begins to set (due to cement hydration), the effective fluid head decreases below the actual pour height. ACI 347.2R provides two design equations:

For columns and for walls poured at rate R ≤ 7 ft/hr, pour height ≤ 14 ft:

Pmax = Cw × Cc × [150 + 9,000R/T]
where: R = pour rate (ft/hr), T = temperature of concrete (°F)
Cw = weight coefficient (1.0 for normal-weight; 0.87 for lightweight 100 pcf; 1.2 for heavyweight ≥150 pcf)
Cc = chemistry coefficient (1.0 no retarder/accelerator; 1.2 Type III cement or retarder; 0.9 accelerated admixture)

For walls poured at R > 7 ft/hr, or pour height > 14 ft, or pour height > 7 ft for columns:

Pmax = Cw × Cc × 150h (full hydrostatic)
This means a 20-foot wall form with a pump pour rate above 7 ft/hr develops a lateral pressure of 3,000 psf at the base — nearly 1.5 tons per square foot. This is the scenario that has caused multiple fatal form blowouts on NYC construction sites.

The calculated maximum lateral pressure is capped at Cw × 150h (full hydrostatic) as the upper bound. Minimum Pmax is 600 psf.

Pump pours are faster than hand-placing concrete — a common NYC concrete pump can place at 20–40 cy/hr, equating to pour rates of 3–12 ft/hr depending on the pour area. Engineers must obtain the contractor's intended pour rate before finalizing form designs.

NYC DOB PE Stamp Requirements

NYC Building Code §3301.6 specifies when PE-stamped formwork and shoring drawings are required:

  • Clear height of pour or shoring exceeds 6 feet (one story): Virtually all multi-story NYC construction.
  • Formwork supports loads over occupied or public spaces: Any pour above an occupied floor, public sidewalk, or occupied streetbed. This covers almost every renovation project in an occupied NYC building.
  • Reshoring extends through three or more floors: Common in fast-track NYC construction where multiple floors are under construction simultaneously.
  • Any other situation where DOB determines engineering is required.

PE-stamped formwork drawings must be filed with the DOB permit application and be on-site during construction. They must show: shoring layout plan at each level, shore type and size, spacing, base plate size, cross-bracing location and type, and the reshoring load flow analysis.

Shoring and Reshoring Load Flow Analysis

In multi-story construction, the fresh concrete pour on an upper floor is carried by shoring down through lower floors — each of which may still be gaining strength — to the ground or a floor slab with confirmed adequate capacity. A shoring and reshoring analysis is required to confirm that no partially-cured slab is overloaded during construction.

The analysis must track the construction sequence:

  1. Determine the age and concrete strength at each floor level at the time each new floor is poured
  2. Calculate the load delivered to each shored floor from all above-level pours and construction loads
  3. Verify that the concrete at each level has reached sufficient strength (typically 75% of f'c) before it receives construction loads
  4. Identify the critical construction stage — the sequence step at which any slab is closest to overstress
Fast-Track Risk: Fast-track NYC schedules often try to pour a new floor every 3–5 days. At that pace, the floor two levels below a new pour may have only 14-day strength — about 85% of 28-day f'c for most mixes. The reshoring analysis must confirm that even at minimum credible strengths, no floor is overloaded. A structural engineer who approves a pour cycle without completing this analysis exposes the owner, contractor, and themselves to catastrophic liability.

Pour Sequence and Construction Loads

The pour sequence — the order in which concrete is placed across a floor plate — creates asymmetric loads on the shoring that can cause lateral instability. Engineers must consider:

  • Concrete placement typically proceeds from one end to the other or from the perimeter inward — the weight grows progressively on one side of the shoring field
  • The pump line (typically 4-inch or 5-inch steel pipe carrying concrete at 600–900 psi) acts as a concentrated moving load on the form deck
  • Vibrator operation creates dynamic impact loads; powered screed equipment (laser screeds, vibratory screeds) transmits additional dynamic loads
  • Standard pour sequence restriction: do not pour more than 50% of the floor plate weight on one side of any selected column line without confirming stability of the shoring

Special Inspections for Formwork

NYC BC Chapter 17 §1705.3 requires special inspection of concrete forming and placing. The engineer of record must include formwork inspection requirements in the Statement of Special Inspections (SOSI). Key inspection tasks:

  • Pre-pour formwork inspection: The special inspector performs a pre-pour inspection — confirming shores are plumb, positioned per the layout plan, fully engaged (base plates bearing, screw jacks extended within limit), cross-bracing is in place, form sheathing is sound without gaps or damaged panels, and embed items (anchor bolts, conduit sleeves) are secure
  • Concrete placement inspection: Placement rate is confirmed to not exceed the rate assumed in the formwork design; pump pressure is monitored; vibration duration and depth per ACI 309 (vibrator overlap, maximum vibrator spacing)
  • Cylinder sampling: Concrete test cylinders cured under field conditions are required to confirm concrete has reached the contractual minimum strength before shores are stripped. NYC DOB typically requires 28-day cylinders for all structural concrete; engineers may specify 7-day cylinders to evaluate early stripping viability
  • Reshoring verification: Inspector confirms reshores are set at each required level before the level above is poured

Formwork Failure: Causes and Prevention

According to OSHA's construction fatality statistics, formwork collapses are among the most lethal construction incidents. The dominant causes in documented NYC-area incidents:

  • No engineering at all: Contractors who self-design formwork without a PE on informal rules of thumb are the single largest cause of catastrophic failures. Construction crews have inherent incentives to minimize shoring (cost and schedule) without an independent engineering judgment to counterbalance.
  • Rapid pump pours exceeding design assumptions: A form designed for a 3 ft/hr pour rate that is actually poured at 9 ft/hr develops approximately twice the design lateral pressure — enough to blow out wall form ties.
  • Shore base settlement or punch-through: Shores set on unsupported wood mud sills over soft or wet ground, or on slab with a void below (from soil settlement), settle suddenly under load. Base plate sizing must be appropriate for the substrate.
  • Premature shoring removal: Removing shores before the concrete cylinder breaks confirm adequate strength — often driven by owner schedule pressure — transfers loads to under-strength slabs.
  • No lateral bracing: Slender shore props without adequate cross-bracing buckle under destabilizing lateral effects of the pour sequence, equipment movement, or wind.
  • Damaged or undersized shores: Using bent, kinked, or corroded Acrow props that have significantly reduced capacity. Every shore prop should be inspected for damage before use on-site.

Stripping Criteria: When Can Shores Be Removed?

Shoring cannot be stripped until the concrete has achieved sufficient strength to carry the loads that will be placed on it after stripping. ACI 347 provides minimum stripping criteria, but structural engineers typically impose more conservative project-specific requirements:

ElementACI 347 Minimum CriterionCommon NYC Practice
Slabs (spans ≤ 10 ft)f'c ≥ 75% of 28-day strength75% confirmed by cylinders
Slabs (spans 10–20 ft)f'c ≥ 85%85–90% with QC cylinder break
Slabs (spans > 20 ft)f'c ≥ 100%28-day cylinders, plus check for long-term creep
Walls and columnsf'c ≥ 50% (typically 12–24 hrs at 70°F)24–48 hrs minimum for exposed architectural concrete
Beams (clear span ≤ 10 ft)f'c ≥ 75%75%
Beams (clear span > 10 ft)f'c ≥ 85%85–100%

In cold weather (below 50°F ambient), concrete gains strength significantly more slowly. NYC winter construction requires heated enclosures, insulated blankets, or heated concrete mixes to meet stripping criteria — and the structural engineer must account for the reduced strength gain rate in the stripping schedule.

Formwork engineering or reshoring analysis for your NYC concrete project?

Asvakas Engineering provides PE-stamped formwork drawings, shoring and reshoring load flow analyses, and Statement of Special Inspections for concrete construction projects in New York City.

Request a Consultation

Frequently Asked Questions

When does formwork engineering require a PE stamp in NYC?

NYC BC §3301.6 requires PE-stamped formwork and shoring drawings when the clear height of the pour or shoring exceeds 6 feet, formwork supports loads over occupied or public spaces, reshoring extends through three or more floors, or the DOB determines engineering is required. This covers virtually all commercial and multi-family concrete construction in NYC.

What is the lateral pressure of fresh concrete for formwork design?

ACI 347.2R formulas calculate lateral pressure based on pour rate, temperature, concrete chemistry, and pour height. For pump pours above 7 ft/hr, full hydrostatic pressure governs: Pmax = 150h psf. A 20-foot wall poured at high rate generates 3,000 psf at the base — more than 10 times what contractors often assume. Engineers must obtain the contractor's actual pour rate before finalizing form designs.

What causes formwork collapses on construction sites?

The most common causes are: no engineering analysis; pour rates exceeding design assumptions (generating excess lateral pressure); premature shore removal before concrete gains adequate strength; inadequate lateral bracing against pour-sequence eccentricity; shore base settlement on soft substrates; and using damaged or undersized shore props. Many NYC collapses involve a combination of these factors, typically without a PE having reviewed the formwork system.

What is reshoring and when is it required in NYC?

Reshoring maintains temporary shores below each freshly poured floor, transferring construction loads down to hardened floors while each new pour gains strength. In multi-story NYC construction, freshly poured concrete slabs cannot yet carry their own weight plus construction loads — reshoring transfers that load to lower floors already at design strength. A shoring/reshoring load flow analysis is required to confirm no partially-cured slab is overloaded at any construction stage.

What special inspections are required for formwork in NYC?

NYC BC Chapter 17 §1705.3 requires special inspection of concrete placement. Inspectors perform a pre-pour formwork inspection (verifying shore placement, bracing, and form integrity), monitor pour rate and vibration during placement, collect concrete cylinders, and verify cylinder breaks before shores are stripped. The engineer of record must list all required formwork inspections in the Statement of Special Inspections submitted with the DOB permit.